Downtown Auburn Progress July 2022

On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.

Every step is taken to ensure compliance with the plans and specifications.  This includes but is not limited to:

  • Soil density testing
  • Concrete and materials testing
  • Footing and reinforcing inspections
  • Pavement testing

In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.

Recently Completed Activities

Site:

  • 100% completion of ponds

Building:

  • First floor framing complete
City Hall from above

City Hall from above

Current Activities

Site and Building Completion

Site:

  • Erosion control
  • Sewer work for Harmony development
  • Grading work for Harmony development

Building:

  • Procurement
  • Submittals and shop drawings
  • Exterior cast stone installed
  • HVAC on first floor
  • Fire suppression system installed in basement
Auburn City Hall with flag
Full site

Upcoming Activities

Site:

  • Mobilization for curb & gutter                     
  • Installation of utilities

Building:

  • Second floor pour of concrete
  • Sally-port concrete pour
Full site

Full site