Downtown Auburn Progress May 2022
On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.
Every step is taken to ensure compliance with the plans and specifications. This includes but is not limited to:
- Soil density testing
- Concrete and materials testing
- Footing and reinforcing inspections
- Pavement testing
In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.
Recently Completed Activities
Site:
- Install fabric & baskets
- Fill dirt
- Grading for Pond A
- Laid out and installed water vaults
- Irrigation sleeve installation
Building:
- CMU installation at evidence room
- Elevators delivered and stored
- Steel delivered
City Hall Steel Erection
Current Activities
Steel Erection full building
Site:
- Erosion control
- Grading for curb
- Band curb install
- Sewer work for Harmony development
Building:
- Procurement
- Submittals and shop drawings
- Sally port CMU installation
- Setting and adjusting steel
- Metal deck install
Curb Installation
Upcoming Activities
Site:
- Curb/gutter
- Fine grade road/swales
Building:
- 1st slab on deck pour
- 2nd floor joist
Full sight