Downtown Auburn Progress August 2021
On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.
Every step is taken to ensure compliance with the plans and specifications. This includes but is not limited to:
- Soil density testing
- Concrete and materials testing
- Footing and reinforcing inspections
- Pavement testing
In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.
Recently Completed Activities
Site:
- Stripping of topsoil
- Mass grading
- Pond C
- Pond B outside wall
Building:
- Rebar fabrication
- Cupola shop drawings
- Building excavation
Pond B Outside Retaining Walls
Current Activities
City Hall Foundation Excavation
Site:
- Pond B inside wall
- Storm drainage – 85% complete
- Sanitary sewer – 85% complete
Building:
- Procurement
- Submittals and shop drawings
- Foundations
Upcoming Activities
Site:
- Pond A
- Water lines
- Roadways and swales
Building:
- Foundation walls
- Concrete masonry units (concrete block)
For more details about Downtown Auburn's redevelopment activities, subscribe HERE to receive email updates.
6th Street
|
|
|