Downtown Auburn Progress June 2021

On-site work continues on Downtown Auburn’s Municipal Complex and infrastructure for the area. Here’s the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.

Care is taken to ensure compliance with the plans and specifications. This includes but is not limited to:

  • Soil density testing
  • Concrete and materials testing
  • Footing and reinforcing inspections
  • Pavement testing

In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.  

Recently Completed Activities

  • Stripping of topsoil
  • Mass grading
  • Steel procurement
  • Electrical procurement
  • Elevator procurement
  • Plumbing procurement
  • Fire protection
  • Metal trusses
  • New power poles
Site and Building Completion

Construction draw completion rate

Current Activities

City Hall Location

City Hall Location

  • Intermediate Erosion Control
  • Site demolition
  • Storm drainage
  • Sanitary sewer
  • Retaining walls – Pond C
  • Fine grading roads and swales
  • Building excavation
  • Rebar shop drawings
  • Procurement of materials

Upcoming Activities

  • Pond B retaining walls
  • Building foundations
  • Selection of exterior finishes

For more details about Downtown Auburn’s redevelopment activities, subscribe HERE to receive email updates

Future Parking Lot

Wall at future parking lot